In the first two weeks of June, a significant road surface renovation project was carried out at the Hanssonkurve on the A23 highway in Vienna. In total, 105 m³ of rapid-hardening concrete was used to renovate an area of 420 m² of road surface. The entire project took place at night to minimize traffic disruption. Work on replacing the concrete slabs began at 10:00 PM each night, and by 5:00 AM, the road had to be ready for reopening to traffic. During these seven hours, sections of the road surface were first removed, and then the new concrete was poured. By 5:00 AM, the highway had to be completely reopened for traffic.
Thanks to the use of Concretum Q-FLASH 2/20 rapid-hardening concrete, up to three concrete slabs could be replaced each night. Between 15 and 25 m³ of concrete were placed nightly. The concrete was produced at the Bau Beton batch plant in Semmering, approximately a 15-minute transport time from the project site. The concrete remained workable for about 90 minutes, and just one hour after the start of setting, it reached a compressive strength of approximately 20 MPa, which was sufficient for traffic release.
Thanks to the use of Concretum fast concrete, it was possible to replace up to 75 m² of road surface per night without restricting traffic or causing queues and bottlenecks. The project was made possible by the positive collaboration with HABAU and Bau Beton GmbH
Product
Country
Austria
Construction Period
2025, May – June
Client
ASFINAG
Construction Company
HABAU
Concrete Producer
Bau Beton GmbH
Concrete Volume
105 m3
Area
420 m2