Product
The arrestor beams on Runway 16 at Zurich Airport required structural rehabilitation. In order to avoid any disruption to flight operations, the project was carried out in several night-time work phases. The concrete surface was removed using high-pressure water jetting and subsequently exposed areas were cleared using a suction excavator. The rapid-hardening concrete Concretum® Q-FLASH 2/20 was then placed and compacted. The nightly construction schedule was as follows:
| 00:00 - 01:30: | Removal of existing concrete using high-pressure water jetting |
| 01:30 - 02:30: | Suction excavator in operation |
| 02:10: | Production of rapid-hardening concrete at Ebirec plant |
| 02:30 - 03:30: | Placement of rapid-hardening concrete |
| 03:40: | Start of concrete setting process |
| 04:10: | Concrete trafficable for surface cleaning |
| 05:00: | Runway released for operations |
Concretum's rapid-hardening concrete was formulated to provide a working time of 90 minutes. Approximately one hour after the onset of setting, a compressive strength of >16 N/mm² was achieved. Runway release was required by 05:00.
Thanks to the use of Concretum high-performance rapid-hardening concrete, the arrestor beams could be rehabilitated without any impact on ongoing airport operations.
Product
Country
Switzerland
Construction Period
2019, July
Client
Flughafen Zürich AG
Construction Company
STRABAG AG, Planer: F. Preisig AG
Concrete Producer
Eberhard Bau AG
Field of application
Air traffic areas